Sr No. | Name Of Project | State | Name Of Client | Project Length (in Km) | Contract Value in Crores |
---|---|---|---|---|---|
1 | Production of Bituminous Mix for patchwork site / paver site including laying & rolling with road Widening / Resurfacing work along with Comprehensive Maintenance Contract for 5 Years according to the specifications for Ahmedabad Municipal Corporation. | Gujarat | Ahmedabad Municipal Corporation | - | 272.00 |
2 | Development of street at Sargasan, canal, Sardar chawk and Raysan, Gandhinagar | Gujarat | PSP Projects Ltd | - | 39.51 |
3 | Upgradation to 6 lane with paved shoulders of Bamanbore to Sayla section of NH8A ( New NH-47) from Km 138+000 to Km 182+490 on EPC mode in the state of Gujarat. | Gujarat | Executive Engineer NH Division,Rajkot | 37.622 | 208.00 |
4 | Upgradation of 6 lane with paved shoulders of Bagodara-Limbdi section of NH 8A (New NH47) from km. 56+000 to km 99+000 on EPC mode in the state of Gujarat (Design Chainage Km 83+655 to Km 126+720) | Gujarat | Executive Engineer R & B Division, Ahmedabad & Rajkot | 44.065 | 283.78 |
Sr No. | Name Of Project | State | Name Of Client | Project Length (in Km) | Contract Value in Crores |
---|---|---|---|---|---|
1 | Construction of Four lane Road of Ankleshwar-Zagadia-Rajpardi- Pratapnagar-Rajpipla Road Km. 0/00 to 14/00 Dist. Bharuch (Section upto Tavdigam) (Balance work) | Gujarat | Executive Engineer R & B Division, Bharuch | 14 | 78.00 |
2 | Construction of Four lane Road of Ankleshwar-Zagadia-Rajpardi- Pratapnagar-Rajpipla Road Km. 14/00 to 44/00 Dist. Bharuch (Section upto Tavdigam) (Balance work) | Gujarat | Executive Engineer R & B Division, Bharuch | 30 | 52.00 |
3 | Widening into Four Lane of Shihori-Patan-Unjha-Visnagar road km. 56 000 to 87 400 Ta.Mehsana Visnagar Dist. Mehsana. | Gujarat | Executive Engineer, R & B Division Mehsana | 31 | 29.74 |
4 | Ahmedabad Municipal Corporation road in diffrent ward | Gujarat | Ahmedabad Municipal Corporation | - | 12.41 |
5 | Expansion of Dadumajra Sanitary Landfill site - Civil and Allied work under Chandigarh Smart City. | Chandigarh | Chief General Manager Chandigarh Smart City Limited | - | 12.40 |
6 | Construction four lanes Road Dabhoi Tilakwada Road (Km. 31/0 to 50/0 through EPC contract | Gujarat | Executive Engineer, District R&B Division, Vadodara | - | 24.78 |
7 | Upgradation of Industrial Infrastructure work at "Dediyasan G.I.D.C. Ind. Estate (Project-III) under the AII Scheme Dist-Mehsana. | Gujarat | Dediyasan Industrial Estate Association | - | 25.15 |